ATLANTIC BEACH, Fla -Wednesday, the crew worked through the day, completing the dewatering of the starboard voids in preparation for completing repairs on the port void salvage hatches and preparing for the dewatering and the pulling effort.

CAPT. TIBB worked throughout the day, transferring personnel and supplies. The STEPHAN DANN and THOMAS DANN will remain on location Wednesday night.

Thursday, with improving sea conditions in the forecast, Global will be conducting dive operations to access and repair the salvage hatches on port vids #2 &3.

The FARRELL 256 will depart for the BRIDGEPORT to support dive operations.

Health and safety of the community and responders plus the protection of the environment are the top priorities of the unified response.